Lindian Resources (LIN) Q3 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 TU earnings summary
11 Jun, 2026Executive summary
Transitioned Kangankunde Rare Earths Project from enabling works to full-scale construction, with EPC contractor mobilised and long-lead equipment ordered targeting first ore feed and concentrate in November 2026.
Acquired 100% of the operational SARECO Mixed Rare Earth Carbonate (MREC) facility in Kazakhstan for US$15 million, enabling integrated upstream and downstream rare earths production.
Achieved over 500,000 lost-time injury-free work hours at Kangankunde, with a workforce of approximately 740 personnel on site.
Tipume accommodation camp became operational ahead of schedule, supporting workforce mobilisation.
ANSTO confirmed Kangankunde monazite concentrate is exempt from radioactive transport classification, providing a significant logistics and commercial advantage.
Financial highlights
Ended the quarter with $42 million in cash, excluding proceeds from a subsequent A$100 million placement and US$11.6 million facility.
Received $5.0 million from the exercise of options during the quarter.
Spent $17.5 million on construction activities at Kangankunde, a reduction of $19.2 million from the previous quarter.
Exploration expenditure was approximately $291,000, up $31,000 from the prior quarter.
Payments to related parties and associates totaled approximately $0.51 million for director and consulting fees.
Outlook and guidance
First ore feed and concentrate production at Kangankunde targeted for November 2026; MREC production at SARECO expected in Q4 2026.
Stage 2 drilling and resource update expected by end of June 2026, aiming to double monazite concentrate output.
June quarter priorities include advancing construction, equipment delivery, power infrastructure, and SARECO due diligence.
Latest events from Lindian Resources
- Construction advances at Kangankunde, targeting Q4 production and strong market positioning.LIN
Diggers & Dealers Mining Forum 2026 - Kangankunde construction accelerates, 100% ownership secured, and cash at A$56.97 million.LIN
Q2 2026 TU - Kangankunde construction and mining milestones achieved; fully funded for Q4 2026 first production.LIN
Q4 2026 TU - Kangankunde Rare Earths Project advanced with robust economics, $35M raised, and net loss reduced.LIN
H2 2024 - Kangankunde project fully funded and under construction, with net loss of $8.79M and strong cash reserves.LIN
H1 2026 - $15M JV secures operational MREC plant, fast-tracking low-cost, ex-China rare earth supply.LIN
M&A announcement - Kangankunde fully funded to production with expanded licence, Iluka partnership, and strong cash position.LIN
Q1 2026 TU - Strategic funding and partnerships secured for Kangankunde; net loss widened to $9.29M.LIN
H2 2025 - Kangankunde secures funding, strategic offtake, and robust economics for rare earths production.LIN
Corporate Presentation