Lindian Resources (LIN) H2 2025 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2025 earnings summary
12 Oct, 2025Executive summary
Achieved major milestones at Kangankunde Rare Earths Project, including a strategic partnership with Iluka Resources, a $91.5 million institutional placement, and Final Investment Decision (FID) approval for Stage 1 development.
Advanced construction at Kangankunde, with site access roads, infrastructure, and early works completed ahead of schedule and on budget.
Secured a 15-year offtake agreement and $20 million construction loan from Iluka, providing revenue certainty and de-risking project funding.
Expanded Kangankunde’s mining licence from 900ha to 2,500ha, supporting future growth and Stage 2 expansion.
Strengthened management team and stakeholder engagement, including key executive appointments and community initiatives in Malawi.
Financial highlights
Net loss after tax for FY2025 was $9.29 million, compared to $4.89 million in FY2024.
Revenue and other income totaled $277,599, down from $421,051 in the prior year.
Net assets at 30 June 2025 were $58.36 million, down from $63.21 million at 30 June 2024.
Cash and cash equivalents at year-end were $3.49 million, compared to $13.25 million in the previous year.
Share-based payments expense increased to $2.68 million (FY2024: $1.20 million).
No dividends declared or paid during the year.
Outlook and guidance
Fully funded for Stage 1 Kangankunde development, with first production targeted for Q4 2026.
Proceeds from the $91.5 million placement to support Stage 2 expansion studies and increase Kangankunde ownership to 100%.
Ongoing focus on advancing bauxite assets in Guinea and Tanzania, with new lease and royalty agreements in place.
Latest events from Lindian Resources
- Construction advances at Kangankunde, targeting Q4 production and strong market positioning.LIN
Diggers & Dealers Mining Forum 2026 - Kangankunde construction accelerates, 100% ownership secured, and cash at A$56.97 million.LIN
Q2 2026 TU - Kangankunde construction and mining milestones achieved; fully funded for Q4 2026 first production.LIN
Q4 2026 TU - Full-scale construction and a strategic acquisition position the company for integrated rare earths production in 2026.LIN
Q3 2026 TU - Kangankunde Rare Earths Project advanced with robust economics, $35M raised, and net loss reduced.LIN
H2 2024 - Kangankunde project fully funded and under construction, with net loss of $8.79M and strong cash reserves.LIN
H1 2026 - $15M JV secures operational MREC plant, fast-tracking low-cost, ex-China rare earth supply.LIN
M&A announcement - Kangankunde fully funded to production with expanded licence, Iluka partnership, and strong cash position.LIN
Q1 2026 TU - Kangankunde secures funding, strategic offtake, and robust economics for rare earths production.LIN
Corporate Presentation