30 Jul, 2026Executive summary
Advanced from site establishment to active construction at Kangankunde, with major contracts awarded for processing plant and non-process infrastructure.
Mobilised Komatsu mining fleet and began construction of Tipume accommodation camp, supporting ramp-up of site activity.
Achieved 100% ownership of Kangankunde, securing full strategic and operational control.
Hosted a US government delegation and increased international engagement, highlighting Kangankunde's strategic importance.
Maintained strong safety performance, surpassing 100,000 work hours without a lost time injury.
Financial highlights
Ended the quarter with A$56.97 million in cash.
Received $9.7 million from the exercise of options during the quarter.
Major payments included US$10 million (A$15.1 million) for final Kangankunde acquisition tranche and $19.3 million for equipment and project costs.
Quarterly cash outflows included $31k for exploration and $19.3 million for construction activities.
Estimated 17.9 quarters of funding available at current expenditure rates.
Outlook and guidance
First production at Kangankunde remains on track for Q4 2026, with construction and commissioning progressing as scheduled.
Ongoing international engagement and offtake discussions to secure future sales and partnerships.
Latest events from Lindian Resources
- Construction advances at Kangankunde, targeting Q4 production and strong market positioning.LIN
Diggers & Dealers Mining Forum 2026 - Kangankunde construction and mining milestones achieved; fully funded for Q4 2026 first production.LIN
Q4 2026 TU - Full-scale construction and a strategic acquisition position the company for integrated rare earths production in 2026.LIN
Q3 2026 TU - Kangankunde Rare Earths Project advanced with robust economics, $35M raised, and net loss reduced.LIN
H2 2024 - Kangankunde project fully funded and under construction, with net loss of $8.79M and strong cash reserves.LIN
H1 2026 - $15M JV secures operational MREC plant, fast-tracking low-cost, ex-China rare earth supply.LIN
M&A announcement - Kangankunde fully funded to production with expanded licence, Iluka partnership, and strong cash position.LIN
Q1 2026 TU - Strategic funding and partnerships secured for Kangankunde; net loss widened to $9.29M.LIN
H2 2025 - Kangankunde secures funding, strategic offtake, and robust economics for rare earths production.LIN
Corporate Presentation