Lumina Metals (LMCU) Investor presentation summary
Event summary combining transcript, slides, and related documents.
Investor presentation summary
3 May, 2026Project scale and resources
Three large sediment-hosted copper-silver deposits discovered in Western Poland, including Nowa Sól, one of the largest undeveloped copper and silver projects globally, with a forecasted average annual production (years 1-10) of 290Kt Cu and 28Moz Ag.
Nowa Sól measured and indicated resource: 604Mt at 1.24% Cu and 38.29 g/t Ag; inferred resource: 112Mt at 1.08% Cu and 28.91 g/t Ag.
Sulmierzyce project (150km from Nowa Sól): inferred resource of 308Mt at 2.09% Cu and 31.9 g/t Ag.
Nowa Sól ranks among the largest global copper and silver projects by contained metal.
Poland is #6 globally in copper resource endowment and #1 in silver resource endowment.
Location and infrastructure
Nowa Sól is 25km from KGHM's smelter, with access to skilled labor, highways, rail, and power infrastructure.
The project benefits from EU regulatory stability and proximity to major cities and transportation networks.
Economic highlights and cost structure
Preliminary Economic Assessment (PEA) shows pre-tax NPV7% of US$8.3B and IRR of 20.5%; post-tax NPV7% of US$1.6B and IRR of 10.8%.
By-product AISC averages US$1.17/lb Cu (years 1-10), placing the project in the lower half of the global cost curve.
Pre-production capital cost totals US$6.4B, with capital intensity of US$16,416/t CuEq.
Forecasted annual EBITDA (years 1-10) is US$2.5B, with significant free cash flow generation.