VHM (VHM) Q4 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2026 TU earnings summary
19 Jul, 2026Executive summary
Entered a long-term strategic partnership with Iluka Resources, securing a binding offtake agreement for Goschen Project's Rare Earth concentrate and a $40 million convertible note funding package.
Completed a $5 million share placement to fund early engineering works and operating costs ahead of Final Investment Decision (FID).
Advanced project implementation with retendering of major work packages and progress on operational approvals, targeting late-2027 commencement.
Fully permitted to mine with all major regulatory approvals secured, reducing project risk and accelerating development.
Financial highlights
Cash at quarter end was $13.1 million.
Net cash used in operating activities for the quarter was $804,000; investing activities used $1.9 million; financing activities provided $4.6 million.
Estimated quarters of funding available is 5.81 based on current cash and outgoings.
Exploration and evaluation expenditure during the quarter was $1.4 million.
Outlook and guidance
Targeting late-2027 for commencement of operations at the Goschen Project.
Ongoing discussions with export credit agencies for senior debt facility to further support project financing.
Heavy Mineral Concentrate offtake negotiations are at an advanced stage with several Tier 1 counterparties.
Latest events from VHM
- Secured full regulatory approvals, advanced to 5Mtpa development, and maintained $11.2M cash.VHM
Q3 2026 TU - Goschen Project advances toward 2026 production with key approvals and robust funding.VHM
Q2 2025 TU - Goschen Project advanced with lower capex, first offtake, and narrowed annual loss to $7.1M.VHM
H2 2024 - Goschen Project approvals and capital raisings drive progress, despite ongoing net losses.VHM
H2 2025 - Loss narrowed, funding secured, and Goschen Project advanced toward production.VHM
H1 2026 - Loss narrowed, capital raised, and Goschen Project advanced toward 2026 production.VHM
H1 2025 - Major financing, regulatory milestones, and resource updates position project for 2027 production.VHM
Q2 2026 TU - Major rare earths project in Victoria targets Q2 2027 production with strong government backing.VHM
AGM 2025 Presentation - Goschen project secures approvals, financing, and offtake deals for rare earths production.VHM
Investor Presentation