Peninsula Energy (PEN) H2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2024 earnings summary
31 Mar, 2026Executive summary
Completed major expansion of the Lance Project’s central processing plant, targeting production restart in December 2024 with a ramp-up to 1.8M lbs U₃O₈ per annum by 2028.
Raised A$166 million in equity, ensuring funding through to anticipated positive free cash flow in Q3 2025.
Increased Lance Project mineral resource estimate by 7.8% to 58.0M lbs U₃O₈, with Ross & Kendrick areas up 19.6% to 26.2M lbs.
Signed new long-term uranium sales contracts, bringing total committed sales to 5.8M lbs over 10 years, about 40% of projected production.
Ended the year with zero debt and US$99.85M in cash.
Financial highlights
Revenue: US$11.87M (down from US$40.4M in 2023), reflecting lower uranium sales volume.
Net loss: US$12.41M (vs. US$3.55M loss in 2023), driven by derivative losses and increased corporate/admin costs.
Gross profit: US$1.78M (flat year-over-year).
EBITDA: US$(12.41)M (vs. US$(4.20)M in 2023).
Working capital surplus: US$99.51M (up from US$31.17M in 2023).
Net assets: US$185.2M (up from US$91.1M in 2023).
Outlook and guidance
Production commissioning on track for late 2024; initial 2025 output forecast revised to 0.7–0.9M lbs U₃O₈.
Positive uranium market dynamics expected, with US ban on Russian uranium imports and rising global demand.
Fully funded to sustainable free cash flow, anticipated by Q3 2025.
Latest events from Peninsula Energy
- Reset plan, contract terminations, and resumed production mark a pivotal year amid sector tailwinds.PEN
H2 202531 Mar 2026 - Nuclear energy demand is surging, driving uranium project development and investment opportunities.PEN
JMM & Tribeca Nuclear Energy Forum 202626 Mar 2026 - Half-year loss widened to US$15.3M due to inventory write-downs amid operational reset and new funding.PEN
H1 202615 Mar 2026 - Lance Project ramp-up advances, with robust funding and improved production outlook for 2026.PEN
Q2 2026 TU15 Mar 2026 - Transition to uranium production on track, with first sales expected by mid-2025.PEN
AGM 202413 Jan 2026 - First yellowcake production and major funding secure ramp-up for US uranium supply growth.PEN
Q1 2026 TU21 Dec 2025 - Production resumes with reset contracts, full funding, and strong growth targets for 2025–2027.PEN
Investor Update23 Nov 2025 - Shareholders approved multiple share issues and incentives, with strong proxy support.PEN
EGM 202530 Sep 2025 - Lance Project advances toward full-scale uranium production with strong resources and funding.PEN
Investor Presentation22 Aug 2025