Pantoro Gold (PNR) H2 2024 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2024 earnings summary
1 Apr, 2026Executive summary
Achieved improved operational results each quarter since Norseman operations began, with cashflow positive performance in the second half of FY2024 despite ongoing capital projects.
Major strategic shift at Scotia Mining Centre accelerated transition to underground mining, boosting economic outcomes and feed grade.
Completed sale of lithium, nickel, and copper rights for $30 million, providing financial flexibility and enabling execution of revised mine plan.
Raised $100 million in equity at a premium, repaid Nebari term loan, leaving only a $12.5 million convertible note maturing in June 2027.
Ended the year with $104 million in cash and gold, positioning for further growth and development of additional underground mines.
Financial highlights
Gold production doubled to 71,370 oz (2023: 35,791 oz), all from Norseman.
Revenue rose to $229.4 million (2023: $98.5 million), but cost of goods sold increased to $280.3 million (2023: $152.8 million).
Gross loss of $50.8 million (2023: $54.2 million); net loss after tax of $49.3 million (2023: $74.6 million).
Net cash used in operating activities was $0.6 million (2023: $17.1 million); investing outflows $11.3 million; financing inflows $67.4 million.
Cash and gold on hand at year-end totaled $103.9 million.
Outlook and guidance
Growth strategy targets development of two additional underground mines over the next two years.
FY2025 exploration budget set at $25 million, with drilling at Scotia and Butterfly area commencing September 2024.
Aim to increase production to over 200,000 ounces per annum by replacing lower grade open pit feed with higher grade underground ore.
Latest events from Pantoro Gold
- Record gold output, strong profit, debt-free, and major growth at Norseman in FY2025.PNR
H2 20251 Apr 2026 - Net profit soared to $56.4M on robust gold output and revenue growth at Norseman.PNR
H1 202612 Mar 2026 - Quarterly EBITDA $84M, cash/gold $216.5M, and production guidance at lower end.PNR
Q2 2026 TU22 Jan 2026 - High-grade underground expansion and exploration drive strong growth prospects.PNR
2024 Precious Metals Summit Zurich + Energy Transition14 Jan 2026 - Q3 gold output missed guidance, but EBITDA hit $46.4M and debt fell to US$6.26M.PNR
Q3 2025 TU23 Dec 2025 - Strong financials and high-grade resources drive plans to double gold production.PNR
Diggers & Dealers Mining Forum 202523 Nov 2025 - Returned to profitability with strong revenue growth and robust cash flow from Norseman operations.PNR
H1 202519 Nov 2025 - Production and exploration accelerate, targeting over 200,000oz annual output and major resource growth.PNR
Investor Presentation16 Nov 2025 - Record gold output, low AISC, and strong cash position support ambitious growth plans.PNR
Q4 2025 TU16 Nov 2025