NET Power (NPWR) Q2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 earnings summary
14 Aug, 2026Executive summary
Strategic shift to prioritize rapid deployment of unabated natural gas power generation for large-load customers, especially data centers and AI, with carbon capture deferred to future phases based on market demand and economics.
Suspended development of Oxy-Combustion Cycle technology and fully impaired related assets, with no current plans to resume development.
Project Permian in West Texas is the primary focus, redesigned for co-located demand, with initial phases excluding post-combustion carbon capture but preserving retrofit capability.
Ongoing commercial discussions and customer engagement for Project Permian, with two modular gas turbine generator sets contracted (68 MW nominal gross power) and additional equipment procurement aligned with customer needs.
Emphasis on reliability (99.9% uptime) through multiple smaller units, battery storage, and redundancy.
Financial highlights
Ended Q2 2026 with $310 million in cash, cash equivalents, and investments, and no debt.
Net loss attributable to shareholders was $80.3 million for Q2 2026, with a $193.7 million impairment charge related to suspended technology development.
Operating expenses for Q2 2026 were $209.9 million, up from $90.6 million in Q2 2025.
Total liquidity at June 30, 2026 was $308.4 million, with current liabilities of $17.6 million.
No project-level financing, customer deposits, or partner capital committed for Project Permian as of the release date.
Outlook and guidance
Near-term focus on natural gas power generation with flexibility to add carbon capture as market and financing conditions allow.
No revenue expected until commercial operations commence; FID for Project Permian Phase I not expected in 2026.
Additional capital will be required for equipment commitments and project-level financing; no committed customer deposits or partner capital as of the report date.
Expectation to secure additional power equipment and customer contracts in the coming months.
Anticipate prolonged power supply constraints, especially in ERCOT, MISO, and PJM, potentially lasting into the 2030s or beyond.
Latest events from NET Power
- Permian Basin clean power project targets 80MW by 2029, with $319M liquidity and key partnerships.NPWR
Q1 2026 - Vote on director elections and auditor ratification at the June 2026 annual meeting.NPWR
Proxy filing - Annual meeting to elect directors, ratify auditor, and review governance, compensation, and ESG.NPWR
Proxy filing - First utility-scale clean power plant targets Texas, leveraging patented CO2 cycle and major partnerships.NPWR
Investor presentation - 80 MW clean power project in Texas targets 2029 operations, scalable to 1 GW by 2031.NPWR
Q4 2025 - Registering $750M in securities to fund clean power tech, with major stockholder resale.NPWR
Registration Filing - Advanced clean power projects, maintained $580M liquidity, and signed key supply agreements.NPWR
Q3 2024 - $609M liquidity and project progress keep 2027–2028 milestones on track.NPWR
Q2 2024 - Project Permian delayed for cost control; modular design and strong liquidity drive 2025 focus.NPWR
Q4 2024