Achieved record quarterly revenue of $292 million, up 82% year-over-year, and net profit of $88 million, up 131% from Q1 2025, with adjusted EBITDA of $154 million and a 53% margin.
Gold production totaled 57,850 ounces (up 7%), with Nicaragua contributing 37,941 ounces (+22%) and Colombia 19,909 ounces (-14% due to planned mine sequencing and temporary disruptions); gold equivalent production reached 60,785 ounces, up 10%.
Silver revenue surged 452% to $14 million, with silver sales of 161,766 ounces at an average realized price of $87/oz, driven by improved recovery rates at Hemco.
Strategic progress included environmental permitting for the Porvenir project, inclusion in major mining indices, and acquisition of the Tolima project in Colombia.
Strategic treasury policy increased gold-backed assets to $173 million, supporting liquidity and growth objectives.
Financial highlights
Revenue: $292 million (+82% YoY); Net profit: $88 million (+131% YoY, $0.29/share); Gross profit: $143 million (+122% YoY).
Adjusted EBITDA: $154 million (+116% YoY); EBITDA margin: 53%.
Free cash flow: negative $72 million, impacted by $127 million deployed into gold sale receivables and $23 million into physical bullion.
Cash and equivalents: $44 million; total liquidity (including gold-backed assets): $217 million; net cash position: $8 million.
Loans and borrowings: $36 million; no meaningful leverage.
Outlook and guidance
2026 gold production guidance: 213,000–233,000 ounces; cost guidance: $2,070–$2,170/oz (cash cost), $2,370–$2,470/oz (AISC).
Nicaragua expected to produce 130,000–140,000 ounces at AISC $2,000–$2,100/oz; Colombia 83,000–93,000 ounces at AISC $1,820–$1,920/oz.
Hemco plant expansion on track to reach 2,200 tpd by June and 2,500 tpd by December 2026.
Growth capital expenditures for 2026: $114 million, with 78% allocated to Nicaragua.
Silver production not included in guidance, representing potential upside.
Latest events from Mineros S.A
- Record operational results and ambitious growth plans target 500,000 oz gold by 2030.MINEROS
Mining Forum Europe 202614 Apr 2026 - Record 2025 revenue, profit, and cash flow set the stage for robust 2026 growth and investment.MINEROS
Q4 202519 Feb 2026 - Revenue and EBITDA rose on higher gold prices, but rising costs pressured net profit.MINEROS
Q2 20242 Feb 2026 - Stable gold output, strong dividends, and growth projects drive a positive outlook.MINEROS
Renmark Virtual Non-Deal Roadshow23 Jan 2026 - Profitable gold producer grows in Latin America, prioritizing sustainability and dividends.MINEROS
2024 Precious Metals Summit15 Jan 2026 - Q3 2024 delivered record gold prices, strong profit growth, and revised lower production guidance.MINEROS
Q3 202413 Jan 2026 - Record profit and revenue in 2024, with stable output and higher costs expected in 2025.MINEROS
Q4 20248 Jan 2026 - Record profits, new leadership, $0.10 dividend, and $12M buyback approved amid strong growth.MINEROS
AGM 20257 Jan 2026 - Record revenue and profit in Q1 2025, driven by higher gold prices and output.MINEROS
Q1 20256 Jan 2026