MC Mining (MCM) Q1 2025 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q1 2025 TU earnings summary
10 Jun, 2026Executive summary
Recorded one fatality and one lost-time injury at Uitkomst Colliery, highlighting ongoing safety challenges and focus on zero harm initiatives.
Uitkomst Colliery's ROM coal production dropped 35% year-over-year to 90,069 tonnes due to geological and equipment issues.
Limited activities at Makhado, Vele, and Greater Soutpansberg Projects; Vele operations remain suspended.
Depressed thermal coal prices persisted, while premium steelmaking hard coking coal prices remained elevated but lower than the prior year.
Corporate changes included new leadership appointments and a major equity subscription agreement with Kinetic Development Group.
Financial highlights
Net revenue per tonne at Uitkomst fell 22% year-over-year to $67/t, while production cost per saleable tonne rose 67% to $98/t.
Cash and available facilities at period end totaled $10.8 million, up from $1.2 million in the previous quarter.
Net cash used in operating activities was $4.36 million for the quarter.
Proceeds from equity issues and borrowings totaled $14.2 million during the quarter.
Outlook and guidance
Makhado Project development and funding activities are ongoing, with the project expected to significantly increase future production.
Environmental and water use licensing studies for Greater Soutpansberg Projects are set to begin in H1 CY2025.
Latest events from MC Mining
- Zero LTIs, Makhado commissioning progress, Uitkomst suspended, cash at US$2.9M, coal prices up.MCM
Q4 2026 TU - Losses widened sharply on lower revenue and major cost increases, with funding uncertainty persisting.MCM
H2 2024 - Uitkomst production fell 26% and costs rose 70% as cash reserves dropped to $4 million.MCM
Q2 2025 TU - Makhado progressed on schedule as Uitkomst output and revenue declined, but liquidity improved.MCM
Q3 2025 TU - Losses widened on sharply lower revenue and output, but new equity and loan extension support liquidity.MCM
H1 2025 - Makhado Project advances on schedule as Uitkomst Colliery boosts efficiency amid lower coal prices.MCM
Q4 2025 TU - Losses widened on impairments and lower sales, but KDG funding and cost cuts improved liquidity.MCM
H2 2025 - Makhado Project nears commissioning as safety improves and cash reserves rise to $13.1 million.MCM
Q1 2026 TU - Makhado Project nears commissioning as Uitkomst output drops and liquidity risks rise.MCM
Q2 2026 TU