Lithium Americas (LAC) Q2 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 earnings summary
13 Aug, 2026Executive summary
Thacker Pass Phase 1 targets mechanical completion in late 2027, with commercial production ramp-up in 2028 and full capacity of 40,000 t/y battery-grade lithium carbonate by 2029.
The project is the largest known measured lithium resource in the U.S., with expansion potential up to 160,000 t/y across five phases and an estimated 85-year mine life.
Over 1,600 workers are on site, with peak labor expected later in 2026; all off-site power modifications are complete and energization is on track for Q4 2026.
Strategic partnerships include a JV and 20-year offtake agreement with GM, and significant funding from the U.S. Department of Energy, Orion Resource Partners, and Yorkville Advisors.
Thacker Pass is positioned as a critical domestic lithium supply source, supporting U.S. energy independence and economic growth.
Financial highlights
Net income for the six months ended June 30, 2026 was $6.3 million, reversing a prior-year loss, with Q2 2026 net income at $1.7 million.
Cash and restricted cash totaled $1.3 billion as of June 30, 2026, including $530.3 million at the Thacker Pass JV.
Cumulative capital expenditure for Phase 1 reached $1.8 billion as of June 30, 2026, with 2026 capex guidance of $1.3–$1.6 billion and total Phase 1 construction cost estimated at $2.93 billion.
General and administrative expenses rose to $26.2 million YTD Q2 2026, up from $14.4 million year-over-year.
Total assets increased to $3.54 billion as of June 30, 2026, mainly from DOE Loan advances and ATM program proceeds.
Outlook and guidance
Mechanical completion of Phase 1 is targeted for late 2027, with ramp-up to full production in 2028.
Capex guidance for Thacker Pass Phase 1 in fiscal 2026 is $1.3–$1.6 billion.
Early commissioning of utilities and completion of main concrete work are expected in the second half of 2026.
Definitive capital estimate for Thacker Pass to be completed by end of Q3 2026.
Expansion to Phases 2–5 could increase total capacity to 160,000 t/y, subject to board and investor approvals.
Latest events from Lithium Americas
- Thacker Pass is set to deliver major U.S. lithium capacity with full funding and rapid construction progress.LAC
Corporate presentation - Thacker Pass is set to boost U.S. lithium supply with fully funded, large-scale production by 2028.LAC
Corporate presentation - Q1 2026 marked a return to profit, strong liquidity, and rapid Thacker Pass project advancement.LAC
Q1 2026 - Shareholders to vote on board size, director elections, and auditor appointment at the annual meeting.LAC
Proxy filing - 2025 marked pivotal progress at Thacker Pass, with robust governance and performance-driven compensation.LAC
Proxy filing - Shareholders to vote on Board, auditor, and expanded equity plan after a transformative year.LAC
Proxy filing - Key votes include board size, director elections, auditor appointment, and equity plan approval.LAC
Proxy filing - Up to $1B in securities registered to fund lithium project development and corporate needs.LAC
Registration filing - Thacker Pass construction advances with strong funding and workforce ramp-up to meet U.S. lithium demand.LAC
Q2 2025