KEFI Gold And Copper (KEFI) H1 2026 earnings summary
Event summary combining transcript, slides, and related documents.
H1 2026 earnings summary
29 Sep, 2026Executive summary
Launched full development of the Tulu Kapi Gold Project after securing a $240 million senior debt facility and completing an equity risk capital package.
A serious security incident at Tulu Kapi in September 2026 resulted in multiple fatalities, including a company employee, leading to immediate suspension of development activities.
Community, government, contractors, lenders, and investors reaffirmed support for the project and the company's cautious approach to resuming development.
Saudi Arabian joint venture GMCO advanced exploration and feasibility studies, secured new licenses, and was selected for a $180 million government exploration program.
Financial highlights
Net assets increased to £87 million as of 30 June 2026 (31 Dec 2025: £57 million), reflecting the March 2026 placement.
Comprehensive loss for H1 2026 rose to £4.6 million (H1 2025: £3.1 million), mainly due to higher administration expenses (£4.3 million vs £2.4 million year-over-year).
Net cash from financing activities was £34.2 million, driven by share placements and royalty financing.
Cash and cash equivalents at period end were £18.3 million (H1 2025: £1.1 million).
Outlook and guidance
Project development at Tulu Kapi remains suspended pending establishment of a secure operating environment; management is closely monitoring expenditure and has deferred further financing drawdown.
The company retains sufficient capital reserves and standby facilities to meet obligations during the suspension.
It is too early to assess the impact of the suspension on project timetable, costs, or financing conditions.
Latest events from KEFI Gold And Copper
- Tulu Kapi and Saudi projects advance toward production, targeting 180koz/year output.KEFI
Investor presentation - Tulu Kapi advances on schedule with strong funding, expansion plans, and LSE main market ambitions.KEFI
Investor update - Tulu Kapi project launched with $340M financing; loss before tax £9.7M; strong cash raised.KEFI
H2 2025 - $355M secured for Tulu Kapi, construction underway, and strong returns projected.KEFI
Status update - Tulu Kapi financing nears completion with strong local support and key milestones set for September.KEFI
Investor update - Major resource upgrades and positive regional trends drive project growth and financing momentum.KEFI
Investor update - Funding secured, three-mine diversification, and main market ambitions drive rapid growth.KEFI
Investor update - Tulu Kapi targets mid-2026 gold production as project financing and resource expansion advance.KEFI
H2 2023 - Final contract signings and $320M financing are imminent, with major works and expansion set for 2025.KEFI
Investor update