Ioneer (INR) Q2 2026 TU earnings summary
Event summary combining transcript, slides, and related documents.
Q2 2026 TU earnings summary
3 May, 2026Executive summary
Leach optimization increased unlevered life of mine NPV by 19% to US$2,237 million and IRR by 8% to 18%.
Annual lithium hydroxide and boric acid production increased by 9% and 7%, respectively.
All-in sustaining cash cost for lithium carbonate equivalent is US$4,628/tonne, placing the project in the lowest cost quartile globally.
Ongoing engagement with U.S. government and strategic partners, with boron added to the U.S. Critical Minerals list.
All major federal and state permits for Rhyolite Ridge construction are secured.
Financial highlights
Average annual EBITDA increased to US$417 million with updated project economics.
Total cash and cash equivalents at 31 December 2025 were US$17.9 million.
Exploration and evaluation expenditure for the quarter was US$2.75 million.
No production or development activities occurred during the quarter.
Outlook and guidance
Updated SEC S-K 1300 technical report and completion of strategic partner process targeted for H1 2026.
Final investment decision timing is dependent on strategic partner process outcomes.
Construction expected to take approximately 36 months once commenced.
Latest events from Ioneer
- Cash reserves surged after a $50M equity raise; Rhyolite Ridge advances amid ongoing legal appeal.INR
H1 2026 - Advanced Rhyolite Ridge, secured US Army land lease, and maintained strong cash position.INR
Q4 2026 TU - Shelf registration supports flexible capital raising for a major U.S. lithium-boron project.INR
Registration filing - AGM confirmed strong project outlook, full permitting, and shareholder support for all resolutions.INR
AGM 2026 - Shovel-ready U.S. lithium-boron project with low costs, strong support, and 2029 production target.INR
Investor presentation - US$50M equity raise and full permitting position Rhyolite Ridge for accelerated development.INR
Q3 2026 TU - Improved project economics and secured funding position Rhyolite Ridge for 2026 milestones.INR
H2 2026 - NPV up 38% to $1.9B, costs low, permits secured, and expansion plans underway.INR
Status Update - Rhyolite Ridge advances to construction in 2025, with execution and funding risks actively managed.INR
AGM 2024