Helium One Global (HE1) Investor update summary
Event summary combining transcript, slides, and related documents.
Investor update summary
14 May, 2026Operational update and project progress
Raised £8 million to fund the upcoming extended well test (EWT) at Itumbula West, expected to last 4–6 weeks and critical for project advancement.
Successfully flowed 4.7% helium to surface at Itumbula West-1, a globally significant concentration with no associated hydrocarbons, CO2, or H2S.
EWT operations scheduled to commence July 2024 at Itumbula West-1, with plans to deepen the well by 100–150m to test both basement and Karoo intervals for commercial flow rates.
Owns a truck-mounted drilling rig, enabling rapid deployment and potential revenue from leasing to other operators.
Results from EWT will inform dynamic subsurface modeling and a feasibility study for a mining license application.
Financial and funding strategy
Raised £8m in June 2024, £4.7m in February 2024, £6.1m in December 2023, and £6.3m in September 2023 through subscriptions and placings at varying share prices.
Current market capitalization stands at £70m with 5.3 billion shares in issue.
Recent fundraises were necessary due to operational needs and market conditions, resulting in dilution but ensuring project continuity.
Future funding aims to minimize dilution, with plans to seek industry partners, joint ventures, or debt financing post-EWT.
Infrastructure costs for helium processing are estimated at around $50 million, with modular design to scale with production.
Project milestones and development plan
Tai-3 well recovered a downhole sample of 0.8% helium in Q4 2023.
Phase III appraisal planned for Q3 2024, targeting project deliverability and monetisation within 18 months.
Modular, containerised production facilities to be finalized post-EWT, with minimal on-site civil work required.
First gas and cash flow targeted by end of 2025, contingent on timely license approval and successful EWT.
Ongoing ESIA and feasibility study to support Mining License application.
Latest events from Helium One Global
- Tanzania helium discovery, US expansion, and strong funding drive near-term growth.HE1
AGM 202414 May 2026 - Resolutions passed; major milestones in Tanzania and US with first revenues imminent.HE1
AGM 202514 May 2026 - Helium discovery and US expansion drive asset growth, despite higher losses from impairments.HE1
H2 20248 Apr 2026 - Secured key mining licence, advanced US project, and strengthened financial position for production.HE1
H2 20258 Apr 2026 - Tanzania and Colorado projects advance, with near-term revenue and robust cash position.HE1
H1 20258 Apr 2026 - Transitioned from explorer to producer with first gas in Colorado and key licence in Tanzania.HE1
H1 20268 Apr 2026