Global Atomic (GLO) Q4 2025 earnings summary
Event summary combining transcript, slides, and related documents.
Q4 2025 earnings summary
2 Jun, 2026Executive summary
Advanced development at the Dasa Uranium Project, with significant progress in underground mine and surface infrastructure, moving closer to production.
Achieved one million hours without a lost time incident at Dasa, reflecting strong safety culture.
Maintained construction schedule through multiple equity financings and are pursuing debt/JV options to minimize further equity dilution.
Strong government support from Niger, with high-level engagement and streamlined regulatory approvals.
Financial highlights
Turkish JV processed 70,497 tonnes EAFD and sold 35.2 million pounds of zinc concentrate in 2025.
Share of EBITDA from Turkish JV was $9.5 million in 2025, up from $6.3 million in 2024; share of net income was $2.3 million, up from $1.3 million.
Cash balance of Turkish JV at year-end 2025 was $8.6 million, up from $4.2 million in 2024.
Company cash balance as of December 31, 2025, was $13.1 million.
Management fees and sales commissions from Turkish JV totaled $1.1 million in 2025, up from $0.9 million in 2024.
Outlook and guidance
Actively engaged with a U.S. Development Bank for a debt facility to finance Dasa development.
Negotiating with a potential JV partner for minority interest in Dasa as alternative financing.
Exploring additional non-equity funding options.
Turkish JV expected to process similar EAFD volumes in 2026 as in 2025.
Latest events from Global Atomic
- Dasa targets high-grade uranium production with strong economics and ESG focus, plus zinc recycling.GLO
Corporate presentation - Dasa Uranium Project advances amid financing delays, with robust uranium prices and strong government backing.GLO
Q2 2026 - Q2 2024 marked a return to profitability and continued progress toward Dasa's 2026 production.GLO
Q2 2024 - Dasa Project on track for 2026, major financings secured, Turkish JV returns to profitability.GLO
Q3 2024 - Dasa construction advances, financing progresses, and Turkish zinc JV returns to profitability.GLO
Q1 2025 - Dasa Project nears H1 2026 production as Turkish Zinc JV rebounds and financing advances.GLO
Q4 2024 - Dasa Project advances amid new financing, while Turkish Zinc JV faces lower zinc prices.GLO
Q2 2025 - Dasa Project advanced on construction and financing; Turkish Zinc JV posted strong Q3 results.GLO
Q3 2025 - Dasa Project advances amid strong uranium and zinc markets, with robust JV earnings and new capital raised.GLO
Q1 2026