28 Sep, 2026Project development and construction progress
Construction is at its peak with 2,000 workers on site and first gold targeted by end of September next year, with the grinding circuit as the critical path for commissioning.
Power plant construction is advancing, with all gensets installed and 65% of project costs committed, reducing risk.
Expansion plans include adding a ball mill, leaching capacity, and power units, with modest initial CapEx and continuous use of the current construction team.
Updated feasibility study results and resource conversion are expected by mid-next year.
Capital allocation will prioritize share buybacks via NCIB, with future strategies to be formalized once Oko West is cash flowing.
Exploration and resource growth
A robust exploration program is underway across three assets, with 55,000 meters of infill drilling planned for Oko West and Ghanie to support an updated feasibility study.
Oko-Ghanie and Oko West are being developed as a single, large project with a 5-kilometer mineralized strike, targeting 500,000 ounces per year.
Exploration at Tocantinzinho (TZ) has identified mineralization 150 meters below current pit limits, potentially extending mine life.
Gurupi exploration is focused on resource expansion, with a PEA expected by year-end and new discoveries along the Chega Tudo trend.
Total production potential is approaching 1 million ounces annually when combining Oko, TZ, and Gurupi.
Strategic outlook and M&A
Recent acquisition of G2 Goldfields has shifted focus to maximizing value from current assets rather than pursuing new M&A.
Gurupi is seen as undervalued and a key growth catalyst, with the upcoming PEA expected to highlight its potential.
District-scale land package post-G2 acquisition is a major exploration focus, with only minor land deals being considered.
M&A remains opportunistic, with no urgent need for new assets unless highly attractive opportunities arise.
Latest events from G Mining Ventures
- On track for >500 koz gold production by 2028, fueled by Oko West and strong cash flow.GMIN
AGM 2026 presentation - Strong Q2 2026 results, record free cash flow, and major project progress amid higher cost guidance.GMIN
Q2 2026 - Transformational gold production growth to 700,000 oz by 2028, led by Tier-1 projects.GMIN
Corporate presentation - Significant construction progress and strategic acquisition drive project advancement and workforce unity.GMIN
Corporate presentation - On track for 500,000+ oz annual gold production by 2028, driven by flagship projects and exploration.GMIN
Corporate presentation - Construction milestones achieved with strong focus on safety, environment, and community.GMIN
Investor presentation - On track for 3x gold production growth by 2028, fully funded and expanding Tier-1 assets.GMIN
Corporate presentation - Record Q3 gold output, strong cash flow, and Oko West construction drive multi-asset growth.GMIN
Q3 2025 - Record gold output, low costs, and major project milestones drive robust 2024 results and 2025 outlook.GMIN
Q4 2024