27 Jul, 2026Reserve and Resource Growth
Group ore reserves increased by 33% to 5.24 million ounces, with mineral resources rising 29% to 8.66 million ounces, using conservative gold price assumptions of A$2,200–A$2,600/oz for reserves.
Karlawinda Gold Project ore reserves grew to 1.57 Moz, maintaining a 10-year mine life at a 150 koz pa run rate, with expansion commissioning underway.
Mt Gibson Gold Project ore reserves rose to 3.68 Moz, including a maiden underground reserve of 365 koz, with further growth expected from ongoing drilling.
Mineral Resource increased to 188.9 Mt at 0.9 g/t Au for 5.67 Moz, up 20% from 2025, including 9.6 Mt at 2.9 g/t for 886 koz underground.
Ongoing drilling at Orion South and Lexington is expected to further grow resources in the short term.
Production and Project Outlook
Medium-term group production outlook is above 400 koz per annum, driven by Karlawinda expansion and Mt Gibson PFS outcomes.
Mt Gibson PFS outlines steady-state production of 260 koz pa over a 19.3-year mine life, with AISC of A$1,870/oz and pre-tax NPV of A$6.1 billion.
Karlawinda expansion to 6.5 Mtpa processing capacity is on track, targeting commissioning in Q1 FY27.
Life of mine for Mt Gibson is 19.25 years, averaging 190,400 ounces per annum for the first 18 years.
96% of production is sourced from Ore Reserves.
Project Development and Optimization
Mount Gibson underground and open pit operations will commence together, ramping up production within 2.5 years of project start.
A second processing hub at Golden Range is being evaluated to process surplus high-grade underground ore from Mount Gibson and open pit ore from Golden Range.
Study work for the second hub targets a PFS and FID in 2027, with capital estimates guided by recent Karlawinda expansion costs (AUD 140 million for 2.5Mtpa).
Detailed design of the processing plant is complete, with procurement to commence in Q1FY27.
Federal environmental permit received; state permitting progressing, with site development targeted for Q2FY27.
Latest events from Capricorn Metals
- Reserve growth and expansion drive a fully funded path to 500,000 oz annual gold output.CMM
Diggers & Dealers Mining Forum 2026 - Annual gold output hit 123,589 ounces with strong cash flow and major expansion projects advancing.CMM
Q4 2026 TU - High-margin gold producer with >4Moz reserves, scaling to 300koz/year and strong cash flow.CMM
Investor presentation - Strong Q3 gold output, record cash flow, and project expansion keep FY26 guidance on track.CMM
Q3 2026 TU - Profit before tax nearly tripled year-over-year, supporting a maiden interim dividend and growth projects.CMM
H1 2026 - Quarterly gold output, record cash flow, and expansion progress support strong FY26 outlook.CMM
Q2 2026 TU - Record revenue, profit, and cash flow; debt-free with major resource and reserve growth.CMM
H2 2025 - Expanding gold projects drive record cash flow, reserve growth, and long-term value creation.CMM
Diggers & Dealers Mining Forum 2025 - Record revenue, profit, and cashflow support growth and development across key gold projects.CMM
H2 2024