Brockman Mining (159) Q3 2026 earnings summary
Event summary combining transcript, slides, and related documents.
Q3 2026 earnings summary
12 Aug, 2026Executive summary
Advanced the Marillana Project with MinRes under the agreed Indicative Development Proposal, focusing on technical, environmental, and social consultation work.
Joint Venture with Hancock Prospecting and MinRes progressed infrastructure studies for new export facilities at Port Hedland.
No mining production or development activities were undertaken during the quarter.
Project activities
Confirmatory studies for Marillana indicate enhanced yields over 45% Fe and product quality above 61.5% Fe.
Sinter testwork shows Marillana Fines can substitute for other Australian fines in Chinese steel mills.
Environmental and water management plans updated; ongoing ecological and hydrological monitoring.
Social Surrounds consultation with Traditional Owners ongoing, in line with updated WA environmental legislation.
Heritage surveys completed at Ophthalmia and scheduled at Duck Creek East for 2026.
Financial highlights
Consolidated cash position at 31 March 2026 was HK$2.8 million.
Net cash used in operating activities for the quarter was HK$4.5 million; year-to-date HK$16 million.
Net cash from financing activities was HK$4.5 million for the quarter.
Estimated quarters of funding available: 7.56, with total available funding of HK$33.8 million.
Latest events from Brockman Mining
- Advanced project development and secured funding, with strong exploration results at Punda Springs.159
Q2 2026 - Marillana Project advances with robust funding, pending regulatory and stakeholder approvals.159
Q1 2026 - Marillana Project advances with robust funding and technical progress, no mining production this quarter.159
Q4 2025 - Project development advanced, cash at HK$4.6M, and funding secured for over eight quarters.159
Q3 2025 - Marillana Project progresses with strong technical results and sufficient funding for near-term activities.159
Q2 2025 - Marillana JV advances with port capacity secured; cash reserves at HK$5.9M, 5.46 quarters funding.159
Q1 2025 - Marillana Project progresses with strong funding and infrastructure partnerships in place.159
Q4 2026 - Net loss narrowed, no revenue, project advancement ongoing, funding and approvals remain key risks.159
H1 2026 - Loss narrowed on lower exploration costs, but going concern risk remains significant.159
H2 2024