Atome (ATOM) H2 2023 earnings summary
Event summary combining transcript, slides, and related documents.
H2 2023 earnings summary
14 May, 2026Executive summary
Aiming to develop the world's largest green fertilizer facility by 2027, with flagship projects in Paraguay (Villeta) and Costa Rica, targeting production in 2027 and focusing on decarbonizing a sector responsible for 5% of global emissions.
Villeta Project in Paraguay is set to be the largest dedicated green fertilizer facility globally, with construction targeted to start by end of 2024 and expected to produce 264,000 tons/year of calcium ammonium nitrate.
Completed FEED for Villeta, selected EPC partners Casale and Urbas, finalized land acquisition, and secured all environmental and operational licenses.
Pipeline includes a 120 MW project in Costa Rica and a 300 MW Yguazu project in Paraguay, both aiming for power purchase agreements in 2024.
Management and board have deep experience in engineering, finance, and fertilizer markets, with strategic investors including Baker Hughes and Schroders.
Financial highlights
FY 2023 loss was US$6.8 million, with nearly US$5 million of development costs capitalized as project assets.
US$5.1 million raised from institutional and private investors in 2023, with management participating at the same share price as new investors.
Additional US$2.5 million raised in early 2024, supported by the chairman and largest shareholder.
Outlook and guidance
Final Investment Decision (FID) and start of construction for Villeta targeted by end of 2024, with commercial production by 2027.
Offtake agreement for Villeta expected to be signed in early Q3 2024; project funding and EPC contract to be finalized in H2 2024.
Aiming to secure power purchase agreements for Yguazu and Costa Rica projects in 2024, advancing both to next development stages.
Latest events from Atome
- $665M secured, 10-year offtake signed, construction imminent, and global pipeline expanding.ATOM
Investor update28 Apr 2026 - Villeta targets 260,000 t/y green fertilizer, $70M EBITDA, and H1 2025 financial close.ATOM
Investor update1 Apr 2026 - Villeta secures full offtake, targets 2027 production, and accelerates green fertilizer expansion.ATOM
Investor update31 Mar 2026 - Villeta Project nears FID, securing Yara offtake and major finance for low-carbon fertiliser growth.ATOM
Investor presentation31 Mar 2026 - Advanced Villeta project financing and execution, with loss of $7.3M and FID targeted for H2 2025.ATOM
H2 202431 Mar 2026 - Villeta project advances toward FID as H1 2024 loss narrows and financing interest surges.ATOM
H1 202431 Mar 2026 - Villeta project secured key financing and advanced toward construction, with losses narrowing per share.ATOM
H1 202531 Mar 2026